IPM was retained by an undisclosed public utility provider to assist in their Facilities Consolidation Project. This capital program involved the conversion of an existing 191,000 sf facility to accommodate and consolidate the existing west-end operations (Fleet, Warehouse, Facilities Group, IT, Administration, Security, etc.) into a single, centralized location to help improve efficiency in operations and service. The project began with detailed property investigations, feasibility studies and concept designs in order to select the most suitable location. The project was completed in phases and started with a full interior demolition and a roof lift before proceeding with building shell and interior renovations. The fast-track construction spanned approximately 20 months and the building was delivered to the Client in accordance with the established schedule and budget.
West-End Operations Centre
Client: Undisclosed Public Utility
Completion Date: November 2016